Reconstruction of air station complex, helicopter pad as well as asphalt concrete layer and road pavement around new constructed buildings for “Azalhelikopter” company
2003 - 2004

Technical specifications and work volumes of the road:

Profiling works with milling machine
1 900 m2
Earthworks
6 068 m3
Capping layer
3 152 m3
Base course
4 100 tons
Asphalt-concrete mixture
7 852 tons

Reconstruction works were started in September, 2003.

Construction works were completed in December, 2004.