Execution of the Works on Highway E-763:
Belgrade – South Adriatic, asphalt concrete construction within the
Sector 1: Belgrade (Ostružnica) – Ljig,
Section 3: Obrenovac – Ub,
Republic of Serbia
2017 - 2018

Technical Parameters and work volumes:

Length
15,37 km
Number of traffic lanes
6 lanes
Width of traffic lane
3.75 m (4 x driving lanes),
2.50 m (2 x emergency lanes),
0.50 m (2 x emergency stopping lane beside median),
0.50 m (2 x emergency stopping lane between driving and emergency lane)
Asphalt works
122.837 tons

Employer: China Shandong International Economic & Technical Branch office Belgrade-Voždovac, Bul. Oslobođenja No. 131, Belgrade, Serbia (Main Contractor)
Contract Duration: August 2017-December 2018

As a subcontractor to the Chinese company China Shandong International Economic & Technical, AzVirt has conduct all works related to the sub-base construction and asphalt works at the Corridor XI, Highway Belgrade- South Adriatic, sub-section: Obrenovac – Ub. The quality of the asphalt achieved in this Project is on the level of highest demands.

The Corridor XI, from Obrenovac to Ljig has been opened for a traffic on August 18, 2019.