Reconstruction of Baku city, Buzovna – Mardakan – Qala motorway
2010 - 2016

Technical specifications and work volumes of the road:

Total length of the road
12,70 km
Width of traffic lane
3,50 m
Number of traffic lanes
4 lanes
Road pavement
265 000 m2
Thickness of asphalt-concrete pavement
240 mm
Earthworks
942 200 m3
Capping layer
83 400 m3
Base course
54 900 m3
Asphalt-concrete mixture
94 500 tons
Various diameter drainage pipes
2 750 pm
Concrete kerb stone
16 300 pm

Construction works were started in December, 2010.

Opening ceremony of Buzovna-Mardakan-Gala Motorway Part I
 

Opening ceremony of Buzovna-Mardakan-Gala Motorway Part I was held on May 26, 2013.

Opening ceremony of Buzovna-Mardakan-Gala Motorway Part I
 

During construction of the motorway the infrastructure has been renewed, lighting system has been established, three junctions have been constructed along the motorway.

Opening ceremony of Buzovna-Mardakan-Gala Motorway Part I
 

Construction works were completed in 2016.